Dam shows potential for green energy

“It’s got to be economically feasible”

The Taylor Dam’s ability to produce hydropower has never been in question. But its economic feasibility has, and over the years since it was constructed 18 miles from Highway 135, that’s been the hurdle.

 

 

But these are different times, and the Taylor Dam is once again being looked at as a source of power. This time around, the Upper Gunnison River Water Conservancy District (UGRWCD), Gunnison County Electric Association (GCEA), and the Uncompahgre Valley Water Users Association are collectively examining the dam’s power potential. A recent “flyover” feasibility study on the project yielded some positive results.
Frank Kugel is general manager for the UGRWCD. “From its inception Taylor Park Dam has always been envisioned to produce power,” said Kugel. “Our district is very supportive of the concept of constructing a hydropower installation at Taylor Park Dam. We feel that it could provide a source of green power while utilizing the water resources in our basin.”
Getting power from the dam to Highway 135 using the existing single-phase cable was deemed economically unfeasible in the past. But according to Kugel, “With today’s interest in green energy and the funding assistance that is available, we felt it was worth a fresh look at generating hydropower.”
Mike Wells, Chief Executive Officer for the GCEA, described the first study as a “20,000-foot flyover on the project.” Half the $30,000 study was paid for with a grant, and the other three entities split the remainder.
 “It did come back feasible, but what it does is take us to the next level where we get into it more in depth,” Wells said. “The next step is a higher reconnaissance feasibility study, more of the design phase, to see what it would look like and how it would work.” Wells said that next phase would assess operational needs and concerns, and possibly take a look at the regulatory agencies that would be required for permitting.
“There would be other players such as the Bureau of Recreation since it’s their dam,” added Wells. “There would have to be an agreement about liabilities, who owns the structure, what sort of lease agreement, compensation and ownership, but these kind of details weren’t looked at during this first step.”
The next level study would cost in the range of $90,000 to $120,000, according to Kugel. “We are currently in the process of seeking sources for that money and we will decide whether to move forward in the next couple months based on [the availability of] those funding sources.”
As far as the price of the project itself is concerned, there is a wide gap between the two main options. Wells said, “An initial estimate—just rough numbers—it’s a $14 million project if we make it into three-phase, or $6.5 million if we size it for the single-phase line. Either would provide a rate of return if we are using average water conditions. If you have a wet year or average year it makes the project feasible. In dry years it’s a losing proposition.”
Wells elaborated on the difference between the existing, underground single-phase line and a three-phase line. “Part of the issue with this project is that we only have a single-phase line that goes from Taylor to Highway 135. The [dam’s hydropower] capacity would have to be downsized.” The single-phase line has a capacity of 1.9 megawatts versus 3.7 for the three-phase. According to Wells, a three-phase line has three wires and three conductors so it has more capacity.
Kugel said there is a “Better opportunity to recoup the costs if we had three-phase.” However, there is a deadline for making the three-phase decision, as they’d need to excavate the old line and bury the new one. “They’re going to repave a six-mile section of the road in 2012, and the cable would ideally need to be installed before then,” Kugel said.
Judging by the rough preliminary numbers provided by Wells, installing the new, higher capacity cable more than doubles the price of the project. But it also improves the project’s payback capacity.
“It’s got to be economically feasible as well as practically feasible,” Wells said. “I can’t risk our membership unless we can verify it will pay back and not damage our members in the form of rates.”
The proposed hydropower generation would not damage fisheries or river hydrology either, according to Wells. “Since that water is so critical to farming operations and fishing, there would be no changes in the river flow. We would not want to mess with any change in streamflows. Our other partners would be very resistant with changing that, it’s just not practical. The stream releases would be as regularly scheduled.
 “In this new energy economy there is an effort move away from coal as a primary [source] for energy generation,” Wells said. “Everybody is excited about local, renewable sources. This next study could really be a kickoff to the project. Not to say there aren’t landmines and pitfalls that could torpedo the project, but this gets us a lot closer.”

Check Also

Crested Butte Briefs

Street party in the future? In her April 15 report to council, town manager Dara …